Integrated Facilities Management (IFM)
PPM Operational Review & Performance Presentation
Multi-Site Operational Reliability & PPM Tracking
Unilever Facilities Management
PPM Execution & Asset Reliability Deck
Executive review covering Subcontractor PPM delivery, In-House maintenance execution, Q4 UHJ target schedule (Weeks 45 to 52), and statutory Life Safety compliance.
Completed PPM
100% Completed
20 Done / 0 OverdueUpcoming Schedule
17 Scheduled
Weeks 1 to 4 AllocationQ4 Targeted Units
62 Assets
Weeks 45 to 52 MatrixLife Safety Systems
187 Detectors
Next Due: Dec 12, 2026Facilities: UHD | AGU | DPC | TMU AUH | UHJ ProjectPress Right Arrow [→] to continue
Slide 2 / 6 — Maintenance Execution
Sites: UHD, AGU, DPC, TMU AUHSubcontractors & Monthly PPM Completion Tracker
PPM Tasks: Nov 2026 vs Dec 2026
Completed Status
20 Done
100% adherence to weekly plan
Upcoming Target
17 Scheduled
Vendors confirmed for W1-W4
Critical Subcontractor DeliverablesNov Status vs Dec Target
| Site | Subcontractor Scope | Nov Status | Dec Target | Vendor / Notes |
|---|---|---|---|---|
| UHD | LIFT - OTIS | Week 3 Done | W3 Scheduled | Monthly Routine |
| UHD | LEGIONELLA TEST - WAFA LAB | Week 2 Done | W2 Scheduled | Water Safety Audit |
| UHD | GREASE TRAP - RED SPOT | W1 & W3 Done | W1 & W3 Sched | Bi-Weekly Cleaning |
| DPC | PEST CONTROL - FIRST RESORT | W1,2,3 Done | W1-W4 Sched | Weekly Scheduled Visits |
| TMU AUH | FIRE FIGHTING - GUARDIAN | Due Dec 2026 | W3 Scheduled | Statutory Certification |
Special Forward Cycles: BMS (Feb 2027), Chiller (Feb 2027), Club Car (Jan 2027) Zero Overdue
Unilever Facilities Management | Operational ReviewSlide 2 of 6
Slide 3 / 6 — Target Roadmap
62 Total MEP AssetsQ4 PPM Target Plan: Weeks 45 to 52 (UHJ Project)
Electrical Units (29 Assets)
Ground Floor DBs, 1st Floor DBs, 2nd Floor DBs, Security Room, Emergency Lights & Pump Room.
Execution: W45-47 & W49-52HVAC Cooling Units (26 Assets)
IDU 1 to IDU 25 across Guard Area, Home Care, Personal Care, Meeting Rooms & Boardrooms.
Execution: W45-W52 StaggeredPlumbing Units (7 Asset Types)
Kitchen Sinks, Wash Basins, Shower Trays, Door Handles, Transfer Pumps across all floors.
November Target: W45 - W48Q4 Weekly Staggered DistributionWeeks 45 - 52
November W45 & W46
Ground Floor DBs, IDU 8 & 12
100% Scheduled
November W47 & W48
1st Floor DBs, IDU 10 & 14
100% Scheduled
December W49 & W50
2nd Floor DBs, Boardroom IDUs
100% Scheduled
December W51 & W52
Emergency Lights, Pump Room, DB 2
100% Scheduled
Unilever Facilities Management | Operational ReviewSlide 3 of 6
Slide 4 / 6 — Electrical Distribution
29 Units Across All FloorsElectrical Distribution Boards: Q4 Target Plan
Week 45 (Nov)
Ground Floor DBs
- • Distribution Board 2
- • Distribution Board 3
- • Distribution Board 4
Week 46 (Nov)
Ground & 1st Floor
- • DB 5 (Ground Floor)
- • DB 6 (Ground Floor)
- • DB 1 (1st Floor)
Week 47 & 49
1st Floor Coverage
- • DB 2, 3, 4 (Week 47)
- • DB 5, 6, 7 (Week 49)
Week 50 - 52 (Dec)
Upper Floors & Pumps
- • 2nd Floor DB 1, 2, 3 (W50)
- • 3rd Floor & Security (W51)
- • Emergency Lights & Pump (W52)
Key Standard: All DB inspections cover thermographic scanning, torque verification, and breaker tripping checks.100% Scheduled in Q4
Unilever Facilities Management | Operational ReviewSlide 4 of 6
Slide 5 / 6 — HVAC & Plumbing
Weeks 45 to 52 SequenceCooling Units (IDUs) & Plumbing Infrastructure
Indoor Cooling Units (IDUs)
26 Units- Week 45 (Nov):IDU 8 (Guard 1) & IDU 12 (Home Care Left)
- Week 46 (Nov):IDU 9 (Guard 2) & IDU 13 (Home Care Right)
- Week 47 (Nov):IDU 10 (Reception) & IDU 14 (Personal Care Left)
- Week 48 (Nov):IDU 11 (Electrical Room)
- Week 49 & 50 (Dec):IDU 15, 16, 19, 20 (Boardroom & Meeting Rms)
- Week 51 & 52 (Dec):IDU 17, 18, 21, 22 (Pantry & Brand Protection)
Plumbing Infrastructure
All Floors- Week 45 Target:Lavatory & Kitchen Sink PPM
- Week 46 Target:Wash Basins & Drainage PPM
- Week 47 Target:Shower Trays & Waste Traps PPM
- Week 48 Target:Door Handles & Hardware PPM
Unilever Facilities Management | Operational ReviewSlide 5 of 6
Slide 6 / 6 — Risk & Statutory Compliance
100% November Compliance CertifiedCritical Life Safety, Fire Protection & MEP Assets
Fire Alarm & Early Warning
- Detectors: 187 Units
- Main Fire Panel: 1 Control Room Panel
- Vesda Panel: 1 Unit (Server Room)
- Leakage System: 1 Unit (5th Floor)
Nov Status: Completed | Next: 2026-12-12
Clean Agent Suppression
- FM200 Cylinders: 6 Cylinders
- CO2 Cylinders: 5 Cylinders
- Pressure Verification: 100% Passed
- Visual Inspections: Completed
Nov Status: Completed | Next: 2026-12-12
Cooling & Power Relays
- FCU Cooling Units: 22 Units
- Split Units: 6 Units (Server Room)
- Electrical Panels: 19 Distribution Panels
- Next Mobilization: December 12, 2026
Nov Status: Completed | Next: 2026-12-12
Next Audit & Inspection Date: December 12, 2026 (All teams mobilized)
Audit Status: Ready for Client Sign-offUnilever Facilities Management | Operational ReviewSlide 6 of 6 — End of Presentation